|
|
Client |
Location |
Description |
| Devon Canada
Energy |
Alberta,
Canada |
Detailed
Engineering, Procurement, Regulatory and Construction
Management for the Tangent Compressor Facility upgrades.
Modifications were made to the main central compressor
site including upgrades to the Flare system and piping
to register the station as a sour facility. |
|
Tullow Developments
Ltd. |
Bangladesh |
Bangora #1 Early Production Facility
Upgrade (120 MMSCFD, Inlet Separation, 7000 BHP
compression, refrigeration/turbo-expander option.)
Metering and construction of a 10" NPS export pipeline
to enable extended testing of the Bangora #1 discovery
well. Scope of Work included Detailed Design (Process,
Mechanical, Civil and Electrical), Module Layout,
Procurement, Construction Management, Commissioning and
Start-up.
|
|
Tullow Developments Ltd. |
Pakistan |
Chachar Gas Field Development consists of a total of
three wells for an aggregate production of 30 MMSCFD.
Surface facilities consists of Separation, Sweetening
for H2S removal, and Dehydration as well as provision
for future compression. Scope of Work includes Detailed
Design (Process, Mechanical, Civil and Electrical),
Module Layout, Procurement, Construction Management,
Commissioning and Start-up. |
|
Tullow Developments
Ltd. |
Pakistan |
Permitting, Engineering,
Procurement, Drafting, Project Management for a 150
MMSCFD gas processing facility for gas containing 15%
nitrogen and 64% CO2. Utilizes the Selexol process with
unique energy recovery solutions to minimize fuel gas
requirements. |
|
Vintage Petroleum Yemen Inc |
Yemen |
TG Engineering was responsible for design and supply of
a dehydration package with a design flow rate of 10
MMSCFD. A self contained skid manufactured in Canada and
shipped to Yemen including inlet separation,
conventional dehydration, hydrocarbon skimming, electric
drive pumps, PLC control panel and programming. |
|
Pakistan Oilfields Limited |
Pakistan |
The Pindori Gas Plant Expansion consisted of
debottlenecking the existing plant to increase capacity
to 50 MMSCFD from 35 MMSCFD by adding refrigeration
capacity, and revamping the LPG fractionation train.
Scope of Work included conceptual and FEED Study with
detailed CAPEX/OPEX estimates. Conceptual study also
included an option for deep cut LPG recovery via
mechanical refrigeration and also by
expansion/recompression. |
|
Devon Canada Energy |
Eaglesham |
Engineering and Project Management for the Eaglesham
area installing wellsites including installation of sour
service separator packages, various line heaters and
associated pipelines. Installation includes all
regulatory, detailed design, procurement and
construction management support. |
|
Devon Canada Energy |
Livingstone |
Permitting, Engineering,
Procurement, Drafting, Project Management for the
Livingstone Coal Bed Methane Pilot Project which
included installing 5 Metering skids, power generation,
a central Pad location located on the side of a
mountain, incineration, on site water storage and
associated pipelines. Installation includes all
regulatory, detailed design, procurement and
construction management support. The Plant is located in
one of the most environmentally sensitive areas in the
province. |
|
Paramount Resources Ltd. |
|
Coordination and review of all of Paramount's facilities
ensuring they conform to all requirements of EUB Guide
60. The review encompassed flaring and venting,
dispersion modeling, review the flare system and
flare-knockouts, ignition systems, make up fuel gas
requirements for acid gas flares, etc. Preparation of a
database for submission to the EUB, and for future
additions to the system. |
|
Duke Energy Midstream |
|
Coordination and review of all of Duke's facilities
ensuring they conform to all requirements of EUB Guide
60. The review encompassed flaring and venting,
dispersion modeling, review the flare system and
flare-knockouts, ignition systems, make up fuel gas
requirements for acid gas flares, etc. Preparation of a
database for submission to the EUB, and for future
additions to the system. |
|
Anderson (Devon) |
Elmworth |
Permitting, Engineering,
Procurement, Drafting, Project Management for the
installation of a grassroots facility for a 50 MMSCFD
(30% H2S) compression and dehydration facility. The
facility included 4 (1680 HP) compressors, mole sieve
dehydration (UOP), inlet slug
catcher/separation. |
|
Anderson (Devon) |
Elmworth |
Permitting, Engineering,
Procurement, Drafting, Project Management for the
installation of 14 Well Gathering Program including
laterals and Main Pipeline (100 km) Facilities included
line heaters/separators, flare system, ESD
stations. |
| Cyries Energy |
Alberta,
Canada |
Regulatory
Applications, Environmental Impact Assessment (SO2 and
NOX dispersion modeling), Process Selection, Detailed
Engineering and Design (Process, Mechanical, Civil,
Electrical, Instrumentation, Automation), Procurement,
Construction Management, Commissioning and Startup of
Sour gas (0.5 Mol% H2S) sweetening facility designed for
an inlet rate of 5.0 MMSCFD gas, 20 BPD condensate, and
10 BPD water. |
|
Anderson (Devon) |
West
Culp |
Permitting, Engineering,
Procurement, Drafting, Project Management for the
installation of 14 Well Gathering Program including
laterals and Main Pipeline. Facilities included line
heaters/separators, flare system, ESD
stations. |
|
Anderson (Devon) |
RyCroft |
Permitting, Engineering,
Procurement, Drafting, Project Management for the
installation of 14 Well Gathering Program including
laterals and Main Pipeline. Facilities included line
heaters/separators, flare system, ESD
stations. |
|
Conoco |
Gilbey |
Permitting, Engineering,
Procurement, Drafting, Project Management for the
installation of Installation of various wellsite
facilities including Inlet Separation and
Pipelines |
|
Gulf Canada |
Richdale |
Process design and analysis and
recommendation for improvements on three (3) GMS/Liquids
plants |
|
Amax Petroleum |
Big
Bend |
Permitting, Engineering,
Procurement, Drafting, Project Management for the
installation of 6 MMSCFD sweetening, dehydration and
processing plant |
|
Blue Range Resource |
Leduc |
Permitting, Engineering,
Procurement, Drafting, Project Management for the
installation of 5 MMSCFD sour gas plant, including inlet
facilities, compression, sweetening &
refrigeration |
|
Blue Range Resource |
Wood
River |
Permitting, Engineering,
Procurement, Drafting, Project Management for the
installation of 12 MMSCFD sour gas plant, including
inlet facilities, compression, sweetening &
refrigeration |
|
Blue Range Resource |
Joffre |
Permitting, Engineering,
Procurement, Drafting, Project Management for the
installation of 10 MMSCFD gas plant including Process
studies and debottlenecking
recommendations |
|
Brigdon Resources |
Stettler |
Permitting, Engineering,
Procurement, Drafting, Project Management for the
installation of 3 MMSCFD gas plant, including inlet
facilities, compression, refrigeration |
|
Brigdon Resources |
Red
Willows |
Permitting, Engineering,
Procurement, Drafting, Project Management for the
installation of 10 MMSCFD Sweet gas plant, 1000 HP
compression |
|
Colin Energy |
Bougie
Creek |
Permitting, Engineering,
Procurement, Drafting, Project Management for the
installation of a 7 MMSCFD sour gas plant, including
inlet facilities, sweetening and
refrigeration |
|
Int. Colin Energy |
Gordondale |
Permitting, Engineering,
Procurement, Drafting, Project Management for the
installation of a 20 MMSCFD sour gas plant, including
inlet sweetening and refrigeration |
|
Morgan Hydrocarbons |
Northstar |
Permitting, Engineering,
Procurement, Drafting, Project Management for the
installation of a 6 MMSCFD, compression, CO2 removal,
dehydration plant |
|
Newport Petroleum |
Hoosier
Area |
Permitting, Engineering,
Procurement, Drafting, Project Management for the
installation of a 5 MMSCFD Joule - Thompson plant and
water disposal system. |
|
Northrock Resources
Ltd. |
Sakwatamau |
Permitting, Engineering,
Procurement, Drafting, Project Management for the
modification of an existing gas plant 10
MMSCFD |
|
Northrock Resources Ltd. |
Ferrier |
Ferrier Gas Plant: Engineering, Procurement,
Construction Management and Commissioning of a gas
plant, inlet separation, compression and refrigeration. |
|
Olympia Energy |
Antelope |
Permitting, Engineering,
Procurement, Drafting, Project Management for the
installation of a 7 MMSCFD sour gas treating facility,
gas gathering, and wellsite facilities |
|
Olympia Energy |
Worsley |
Permitting, Engineering,
Procurement, Drafting, Project Management for the
installation of 10 MMSCFD gas plant, including inlet
facilities, 600 HP compression, refrigeration, gas
gathering facilities |
|
Olympia Energy |
Gordondale |
Permitting, Engineering,
Procurement, Drafting, Project Management for the
installation of 10 MMSCFD gas plant (1800 HP
compression), sweetening, refrigeration, crude oil
battery, gathering system, wellsite
facilities |
|
Olympia Energy |
Bittern
Lake |
Permitting, Engineering,
Procurement, Drafting, Project Management for the
installation of Plant expansion from 4 MMSCFD to 14
MMSCFD, including 800 HP
compression |
|
Olympia Energy |
Cutbank |
Process optimization studies, electric power contract
negotiation, field compression facilities, 600 HP. |
|
Longview |
Penhold |
Penhold Gas Plant: Permitting, Engineering, Procurement,
Drafting, Project Management for the installation of a
sour gas plant, including inlet facilities, compression,
sweetening & refrigeration. | |